By Nerijus Adomaitis

OSLO, Oct 7 (Reuters) -Energy firms Equinor EQNR.OL, Aker BP AKRBP.OL and Vaar Energi VAR.OL have raised their crown-denominate cost estimates for major oil and gas development projects offshore Norway, the country's government said on Monday.

Equinor's Johan Castberg project is now expected to cost 86 billion crowns ($8.08 billion), up from a nominal estimate of 80.3 billion seen one year ago, the government's fiscal budget documents showed.

The oilfield the Arctic Barents Sea is expected to start production by the end of this year, the company has said, two years behind its original schedule.

The field was initially estimated to cost 49 billion crowns to develop, when it was approved in 2018.

Since then, costs have increased by 25.7 billion crowns and by 2.2 billion crowns from a year ago, measured in 2024 crowns, Equinor said in a statement.

The increase from a year ago was due to Castberg's production vessel having to spend more time at a shipyard in Norway, currency effects and a general cost increase, the company said.

Meanwhile, Aker BP's Yggdrasil is expected to cost 134.4 billion crowns, up from nominal 120.2 billion seen a year go, while Vaar's Balder Future will cost 52.2 billion crowns, up from 44.5 billion crowns.

Cost increase measured in 2024 crowns were due to a weaker exchange rate, which contributed to imported inflation, said an Aker BP spokesman, adding that costs measured in U.S. dollars were within previous guidance.

Vaar Energi was not immediately available for comment.

The independent subsidiary of Italy's Eni ENI.MI warned in August that Balder's project costs would increase by pre-tax 4.3 billion crowns due to its startup being delayed until the second quarter of 2025 from end of this year.

Balder's costs have more than doubled from an initial estimate of 19.6 billion crowns in 2019.

Aker BP's Yggdrasil, Norway's largest oil and gas development since the startup of Equinor's Johan Sverdrup oilfield in 2019, is facing legal challenges, with environmental organisations disputing its approval by the energy ministry.

The company, however, has said the project, approved at the end of 2022, is on track to start production in 2027.


($1 = 10.6472 Norwegian crowns)



Reporting by Nerijus Adomaitis, editing by Terje Solsvik and David Evans

</body></html>

免责声明: XM Group仅提供在线交易平台的执行服务和访问权限,并允许个人查看和/或使用网站或网站所提供的内容,但无意进行任何更改或扩展,也不会更改或扩展其服务和访问权限。所有访问和使用权限,将受下列条款与条例约束:(i) 条款与条例;(ii) 风险提示;以及(iii) 完整免责声明。请注意,网站所提供的所有讯息,仅限一般资讯用途。此外,XM所有在线交易平台的内容并不构成,也不能被用于任何未经授权的金融市场交易邀约和/或邀请。金融市场交易对于您的投资资本含有重大风险。

所有在线交易平台所发布的资料,仅适用于教育/资讯类用途,不包含也不应被视为用于金融、投资税或交易相关咨询和建议,或是交易价格纪录,或是任何金融商品或非应邀途径的金融相关优惠的交易邀约或邀请。

本网站上由XM和第三方供应商所提供的所有内容,包括意见、新闻、研究、分析、价格、其他资讯和第三方网站链接,皆保持不变,并作为一般市场评论所提供,而非投资性建议。所有在线交易平台所发布的资料,仅适用于教育/资讯类用途,不包含也不应被视为适用于金融、投资税或交易相关咨询和建议,或是交易价格纪录,或是任何金融商品或非应邀途径的金融相关优惠的交易邀约或邀请。请确保您已阅读并完全理解,XM非独立投资研究提示和风险提示相关资讯,更多详情请点击 这里

风险提示: 您的资金存在风险。杠杆商品并不适合所有客户。请详细阅读我们的风险声明